Sunday, 15 July 2012

16/7/12


Back side of the house.
We went back over scaffolding today to refresh our minds about the names of the members.We then went ahead with the house build.Me and Haydn carried on with the Soffiets,Got all of the ones done that we had access to.200mm centers for the nailing off to the soffiet plate and 830mm centers for the outriggers.The boards slot into the plastic tabs.After this Me and Brad continued on with weather boards.We managed to get ,most of the boards up for half of the house.The cut ends were primed up.Then the boards were nailed to the studs.The next thing we done was grabbed a straight edge and ruled down the boards as to where the studs are behind the boards.Then i used the builders square,and adjusted it to 35mm and marked off where the holes were to be pre drilled.Jolt head 3 inch nails were then nailed in to fix the boards to place.
lounge Window

Window Flashings were also being put in by another group,Hopefully tomorrow I will be able to get stuck into them aswell just to speed things up a bit.The Ceiling battens are basically all in place now and ready for the gib.We should have the windows all tacked and nailed in.The top flashings will be finished tomorrow.

I think we will be starting to build a timber scaffolding in the next week or 2 for our assessments which will be good.

Tuesday, 10 July 2012

11/7/12

So today we got as far as we could with the Facia.We are now waiting for the last piece to arrive to finish it off.I set up a string line with dodge and blocks to re check the outriggers.Some were out due to the timber warping,so i nailed some packers to the end of the outriggers to get a nice straight facia on the house.I then moved on to doing soffits.They were marked at 200mm centers for the flat heads to be nailed into the soffit plate.Then found the centers of the out riggers which were 900mm on the width of the house.and 600mm on the length of the house.Plastic slots were cut at 605mm for the soffit cement board to slot in to.

Getting the Facia to the correct height.

All the Facia that we have done.
I had ago at weather boards as well.The building paper was already chalk lined ready for me to put the weather boards up onto.Brad,used the skilly to cut a slot out of the board for where the back door was.Our ends were painted with primer to prevent rott and swelling by outside conditions.We should have the rest of the weather boards finished next week when we return,along with the Soffiets and facia when the rest of the materials arrive.

A few of the walls have been straightened on the inside as well due to people removing the internal bracing when they should not have.Now the rest of the ceiling battons are being nailed off ready for gib.

Sunday, 8 July 2012

9/7/12

We started off in class working on a subject,Scaffolding.And what it is used for ect.Scaffolding is set up on a building site around the construction or erection of a building.It is very useful for us as builders needing to work on high points of the build,For example,Me and Brad used portable scaffolding on each side of the house.We needed it for the installation of the outriggers for our soffiets.

There are many parts to a scaffold set up;Ledger,Standard,Hand guard,midrail,Kick rail,putt rails,Sole boards.These are some of the components involved in scaffolding.

Aluflex which was attached to the lounge opening.
Aluband along with the plastic corners.



Aluband.

Soffiets.
Once we got back to the E Shed.We went ahead with facia.We got our entire side done,Then we moved onto one of the 7.2m sides of the house,turned out the outriggers were all different lengths,So we had to remove them and re cut them to the correct lengths,A dodgem block was set up as well.A spirit level was used to level the outriggers in place.Then used a nail gun to fix them to place.A few of the other groups were setting up ceiling batten,for the inside.While another group is doing the soffiets.Cement board ws used.200mm centers for the nailing with nails to the soffiet plate.with a nail into every outrigger.Flat head nails were used.Regan and Tom were laying down aluband,Plastic corners were also nailed in before the aluband was laid down,Add 200mm to the bottom length of the band at each end,so 400mm in total.Then clean the surface it is being attached to.After this remove the film on the adhesive surface then place it onto the building wrap around the buildings openings.Once this is all laid out,attach a stip of 50mm by 100mm to each of the corners on a 45 degree angle to prevent the tape from moving or coming off while continuing with the build.